SSL client is Independent Secondary School of the Year for the North West!

SSL are delighted to hear that Withington Girls’ School has been named North West Independent Secondary School of the Year by The Sunday Times and also regained its position in the top 25 elite independent schools in the UK.

Having been engaged with as sports pitch consultant to deliver the reconstruction of the 20 year old synthetic hockey pitch at the school’s site in South Manchester, SSL are thrilled that the dedication and passion of the staff, pupils and everyone involved at the school has been recognised.

And there is cause for double celebration as the redeveloped synthetic hockey pitch has recently achieved FIH (International Hockey Federation) National certification. This means that the SSL designed facility meets all requirements of the FIH Quality Programme for Hockey Turf. Tests include measurements of how the ball interacts with the playing surface, ensures the surface provides well-being and protection for players and includes checks to confirm the pitch has been built to the dimensions, line marking, slope & surface drainage requirements of the FIH.

This means that the facility meets hockey performance standards that are recognised internationally, something that is certainly something the school can be very proud of.

To hear more about the project and the role SSL played, take a look at the project video…

SSL deliver refurb of Cheshire sports courts

Just 37 days since construction started, over 3500m2 of macadam sports courts in Cheshire have been successfully refurbished in a project carefully designed and overseen by SSL.

SSL were first engaged by Helsby High School in May 2018 to provide an independent assessment and outline cost options to refurbish two blocks of old unusable macadam courts. With a preferred option identified, SSL developed a detailed specification document complete with bill of quantities and a suite of design drawings before tendering the scheme to several specialist contractors. Construction works were commenced by Fosse Contracts Ltd on 10th October with SSL carrying our key stage checks during the build to ensure the required industry construction standards were achieved.

The of 29th November saw official project handover, just 37 work days since works commenced!

Despite the winter weather kicking in, the school is now able to increase their sports provision, not just for pupils, but also for the local community.

A time lapse of the construction phase can be viewed at https://www.youtube.com/watch?v=_uQjns35ROI