Just 37 days since construction started, over 3500m2 of macadam sports courts in Cheshire have been successfully refurbished in a project carefully designed and overseen by SSL.
SSL were first engaged by Helsby High School in May 2018 to provide an independent assessment and outline cost options to refurbish two blocks of old unusable macadam courts. With a preferred option identified, SSL developed a detailed specification document complete with bill of quantities and a suite of design drawings before tendering the scheme to several specialist contractors. Construction works were commenced by Fosse Contracts Ltd on 10th October with SSL carrying our key stage checks during the build to ensure the required industry construction standards were achieved.
The of 29th November saw official project handover, just 37 work days since works commenced!
Despite the winter weather kicking in, the school is now able to increase their sports provision, not just for pupils, but also for the local community.
A time lapse of the construction phase can be viewed at https://www.youtube.com/watch?v=_uQjns35ROI